The risk register ranks risks by the dollar value of each risk
according to the operational definition of risk given earlier. Constructing the
risk register on a spreadsheet allows risks to be sorted by dollar value so
that the highest risks are always on top of the list. The risk register also
facilitates keeping all risks in the same data base even though management
actions may be active on only the top five or ten at any time. When a high risk
is mitigated the expected dollar value of the risk is reduced and it falls out
of the top five or ten but is still on the list. This enables reviewing
mitigated risks to ensure they remain mitigated or to readdress a risk at a
later time when all the higher risks have been mitigated to even lower values.
An example of a simple risk register constructed on a spread sheet is shown in
figure 9.
Figure 9. An example
template of a risk register constructed in columns on a spread sheet.
The risk type and impact if risk occurs are usually described
as “if”, “then” statements. This helps the management team remember
specifically what each risk entails as they conduct reviews over the life of
the activity. Expected values are expressed in dollars, which facilitates both
ranking and decisions about how much resources should be assigned to mitigation
activities. I am assuming of course that in managing activities in your
organization it is the practice to hold some fraction of the budget in reserve
to handle unforeseen events. It is this reserve budget that is assigned to risk
mitigation activities. Risk mitigation actions should be budgeted and scheduled
as part on on-going work. A failure many inexperienced managers make is
handling risks outside of the mainline budget and schedule. This undisciplined
approach often leads to risk management degenerating into an action item list
and finally to a reactive approach to unexpected events rather that a proactive
approach to reduce the risks systematically.
A more complete risk register template than the example shown
in figure 9 might contain columns for the risk number, title, description (if),
impact (then), types (three columns: cost, schedule, quality or technical),
probability of occurrence, cost impact, schedule impact, mitigation plan and
mitigation schedule. The form of the risk register template is not critical so
the team managing the risks should construct a template that contains the
information they feel they need to effectively manage risks.
The risk register, if properly maintained and managed, is a
sufficient tool for risk management on small and short duration projects.
Setting aside an arbitrary management reserve budget to manage risks is ok for
small projects. Portions of the reserve are allocated to mitigation of risks
and the budgets and expenses for risk mitigation can be folded into the overall
cost management system. Large, long duration projects or high value projects
warrant a more focused approach to budgeting for risk management.
If you find that the pace
of blog posts isn’t compatible with the pace you would like to maintain in studying this
material you can buy the book “The
Manager’s Guide for Effective Leadership” in hard copy or for Kindle at:
or hard copy or for nook
at:
or hard copy or E-book
at:

I seldom leave remarks, but after reading through some of the comments on "24 B The Risk Register".
ReplyDeleteI do have a couple of questions for you if it's okay. Could it be only me or do a few of these remarks come across as if they are left by brain dead visitors? :-P And, if you are writing at other social sites, I'd like to keep up with
everything fresh you have to post. Could you list of every one of all your shared
sites like your Facebook page, twitter feed, or linkedin profile?
Also visit my webpage Pure GCE REview
Just want to say your article is as amazing. The clearness to your
ReplyDeletepost is simply spectacular and i could think you're a professional in this subject. Well with your permission let me to take hold of your feed to keep up to date with impending post. Thanks a million and please continue the enjoyable work.
My homepage: cheap living room furniture for sale
Slot machines are ѕpeсіficallу prоhibited fгom Class IΙ gaming.
ReplyDelete" keep this in mind whenever you step into a casino. If something sounds like it is too good to be true, most likely it is.
Feel free to visit my web blog :: jeux-de-casino.co